Contemporaneous delay analysis

Windows analysis: measure delay period by period

Cut the project into windows between updates and measure how much the critical path slipped in each — and what drove it.

Update to updateCritical-path slip per windowConcurrency kept visible

Manual planning is available on Free. AI generation requires an eligible paid plan.

D0D20D40D60D80D100D120W1 0dW2 +9dEarthworksDrainageIrrigationPavingPlantingHandover
TimingContemporaneous / retrospective
UsesBaseline + statused updates
MeasuresSlip per window
PlanProfessional · one free trial

How it works in Nexora

  1. Baseline + updatescontemporaneous
  2. 1Define the windowsUpdate to update
  3. 2Measure each windowCritical-path slip
  4. 3AttributeEvents · concurrency
  5. Windows reportslip per period

Start free, upgrade when it pays for itself

Compare every plan →

What windows analysis is

Windows analysis (also called time slice or contemporaneous period analysis) divides the project into periods, usually between consecutive updates, and measures the movement of the forecast completion and of the critical path within each. Because it relies on the updates the project actually produced, it is often preferred for retrospective delay claims.

How it runs in Nexora

  1. Import the baseline and the statused updates (XER files work).
  2. Define the windows — typically update to update, or around key events.
  3. For each window, compare the critical path and completion at its start and end.
  4. Attribute the slip to the events and performance in that window, and record concurrency.
  5. Report the slip window by window with the evidence behind it.

Worked example

Illustrative values only.

WindowPeriodCompletion movementDriver
W1Baseline → update 01 (D30)0 daysOn programme
W2Update 01 → update 02 (D55)+9 daysDrainage productivity, re-estimates (contractor)

A new employer instruction notified at update 02 is a future event at that point; its effect is assessed prospectively with a time impact analysis.

Good practice

  • Use updates that were actually issued, with consistent data dates and settings.
  • Check each update's logic and progress before relying on it.
  • Keep the critical path of each window, not only the completion date.
  • Show concurrent delays and how they were treated.

Why the windows follow the updates

Each update is a snapshot of what the project team believed at the time. Bounding the windows by updates means every measurement uses a programme that existed and was used — the strength of a contemporaneous method. Windows can also be bounded by key events or milestones, as long as the same rule is applied throughout the analysis.

Half-step: separating progress from revisions

Between two updates, the forecast can move for two different reasons: the progress that was recorded, and the changes made to the logic or durations of the remaining work. A half-step (bifurcated) approach first applies only the progress to the earlier update, then the revisions. The slip is split into what performance caused and what re-planning caused — often the decisive distinction in a claim.

Attributing the slip in each window

What to record per window
ItemWhy it matters
Critical path at start and endShows which work drove completion in the window
Completion movement (working days)The slip to be explained
Events active in the windowCandidates for responsibility
Concurrent delaysOverlapping causes on the critical path
Mitigation achievedTime recovered within the window

Windows analysis and the rest of the claim

Windows analysis tells you how much time was lost and when. It is often combined with a time impact analysis for events that are still in the future at the latest update, and with a recovery schedule for the time the contractor intends to win back. Keeping the three separate — measured slip, forecast impact, planned recovery — makes the submission easier to review.

Common questions

What is the difference between windows analysis and TIA?

Windows analysis measures what happened between updates; a TIA forecasts what an event will do from the last update before it.

How many windows should I use?

Usually one per update period, or windows bounded by key events. Consistency matters more than the number.

Can windows analysis show concurrent delay?

Yes. Within each window, overlapping delays on the critical path are identified and reported with their treatment.

Try it on your own programme

Bring a representative work package — a BOQ extract or an XER — and review every assumption with your team.