Build a recovery schedule that CPM can prove

When the forecast slips, compare recovery scenarios against the current programme. Review the critical path, extra resources and construction assumptions behind each option.

Schedule compressionCrashing and fast-trackingScenario review

Manual planning is available on Free. AI generation requires an eligible paid plan.

D0D20D40D60D80D100D120EarthworksDrainageIrrigationPavingPlantingHandoverCRASHFAST-TRACK
SourceThe latest statused update
LeversCrash · fast-track · logic
ProofFull CPM per scenario
PlanProfessional · one free trial

How it works in Nexora

  1. Updatestatused
  2. 1Pick the leversCrash · fast-track · logic
  3. 2CompareEach scenario by CPM
  4. 3ApplyTo a draft revision
  5. Recovery.xerproven finish

Start free, upgrade when it pays for itself

Compare every plan →

Start from the current forecast

A recovery programme should explain how the team intends to regain time. Begin with a reviewed update, then identify the path that drives completion and the constraints that limit available options. Nexora provides recovery planning within the project-controls workspace.

A target finish date is a goal, not evidence that a scenario is feasible. Review quantities, work fronts, crew availability, safety, inspections and procurement before accepting a compressed programme.

Recovery starts from the update — not from a target date

A recovery schedule is a plan to win back time on the programme as it actually stands. Nexora takes the latest statused update as the recovery source; the update itself is never changed. Scenarios are built on top of it, so you can always compare against what the project is really forecasting.

If part of the delay is excusable, keep that separate: the time belongs to an extension of time assessment. Recovery is for the days the contractor needs to win back.

Three kinds of levers

Recovery levers and what they change
LeverWhat changesWatch for
CrashingMore crews, shifts or a faster method shorten a driving activityWork-front limits, congestion, cost per day saved
Fast-trackingWork overlaps with SS / FF links and lags where the sequence allowsReleased areas, inspections, rework risk
Logic changesA different construction sequence on the driving pathConstructability, approvals, interfaces

An automatic search can propose combinations along the driving path. Every proposal is a scenario you review — not a change applied to the programme.

What a good recovery report shows

  • The update used as the source, and its data date
  • Each lever, the activities it touches and the days it buys
  • The new critical path and any near-critical paths that appeared
  • Extra resources, cost and risk per scenario
  • The scenario applied to a draft revision, ready for approval and XER export

Crashing and fast-tracking change different assumptions

Two common recovery levers
OptionWhat changesReview before acceptance
CrashingMore capacity or a changed method reduces an activity durationAchievable output, resource availability, added cost and site congestion
Fast-trackingWork overlaps where the construction sequence allows itReleased work fronts, interface logic, rework risk and approvals

Use these as engineering options, not automatic rules to apply to every activity. Shortening a non-driving activity may have no effect on project completion.

Worked example: three options for a twelve-day chain

Illustrative example: A takes four days, B five days, and C three days. All three form one critical chain with no other constraints.

  • Current forecast: A → B → C, finish-to-start, takes 12 working days.
  • Crash B: reducing B from five to four days gives 11 working days, if the extra capacity is achievable.
  • Overlap A and B: allowing B to start two days before A finishes gives 10 working days, if the released work front and method justify the overlap.

These are separate illustrative scenarios. Neither is an automatic recommendation. A different path can become critical, and a resource limit can remove the apparent benefit.

Make the recommendation reviewable

  1. Keep the current updated programme as the scenario reference.
  2. Document every changed duration, dependency, calendar and resource assumption.
  3. Compare forecast completion, critical paths and resource peaks.
  4. Record cost, access, approval and execution risks with the relevant team.
  5. Obtain project approval before issuing the selected recovery programme.

Use schedule updates to establish the reference forecast. If a delay event also needs assessment, keep the delay analysis and the proposed mitigation clearly documented.

Common questions

Will adding more labour always recover time?

No. Available work fronts, equipment, interfaces and non-labour constraints can limit output. Test the changed duration and resource assumptions.

Is recovery scheduling the same as delay analysis?

No. Recovery compares corrective execution options. Delay analysis assesses the effect of events using a defined programme and method.

Does a compressed schedule guarantee the target date?

No. Review feasibility, resources, approvals and any new critical path before committing to a target.

What is the difference between crashing and fast-tracking?

Crashing shortens an activity by adding capacity; fast-tracking overlaps activities that were in sequence. Both only help if they act on the driving path.

Does Nexora apply the recovery to my programme automatically?

No. Scenarios are measured and compared; the one you choose is applied to a draft revision for review before anything is issued.

Can the Planning Agent help with recovery?

Yes. Describe what changed on site; the agent traces the impact and proposes actions on a draft revision, which you approve or roll back.

Try it on your own programme

Bring a representative work package — a BOQ extract or an XER — and review every assumption with your team.