An update is more than a percentage complete
A weekly or monthly report needs to distinguish what has happened from what is still expected. Actual starts, actual finishes and remaining durations tell different parts of that story. Nexora brings schedule updates into the same workspace as the planning programme.
Before updating, agree the reporting cut-off and collect progress evidence from the site team. Keep the approved baseline available for comparison and distinguish a forecast update from an approved baseline revision.
Key terms in a schedule update
- Data Date
- The cut-off between what has happened (actuals) and what is still forecast. Everything left of it is history.
- Actual start / actual finish
- Recorded dates. They decide what an activity is: no actual start means not started, an actual start without a finish means in progress.
- Remaining duration
- The work left on an in-progress activity, re-estimated at the data date — not simply the original duration minus elapsed days.
- Retained Logic vs Progress Override
- How the schedule treats an activity that started before its predecessor finished. Retained Logic keeps the remaining work waiting for the predecessor; Progress Override lets it continue.
- Out-of-sequence progress
- Work recorded against logic. It is flagged so you can decide whether the logic or the progress is wrong.
- Earned value (EV)
- Planned value, earned value and actual cost compared to give SPI and CPI — schedule and cost performance in one view.
Update straight from your P6 programme
Import the XER your team already maintains. Set the data date, enter actual dates and remaining durations activity by activity, and let CPM reschedule the remaining work on the project calendar. Compare the forecast with the baseline, see the activities now driving completion, and export the statused XER back to P6.
The same update feeds the rest of project controls: a cost-loaded programme followed through to cash flow, S-curves, and the reference forecast for recovery scenarios and delay analysis.
Common update mistakes
- Different cut-off dates for different packages in the same update.
- Percent complete entered without revisiting the remaining duration.
- A status label that disagrees with the actual dates (an activity marked complete with no actual finish).
- Overwriting the baseline instead of keeping it for comparison.
- A narrative that reports dates without explaining what drove them.
Build a repeatable reporting cycle
- Set the data date. Use the agreed cut-off for all packages in the reporting cycle.
- Record actual progress. Reconcile starts, finishes and quantities against the site records.
- Reassess remaining work. Review durations, crew availability, access, approvals and procurement.
- Review the forecast. Inspect milestone movement, critical-path changes and logic around incomplete work.
- Explain the movement. Write a narrative that connects the date change to evidence and an action owner.
Worked example: one extra remaining day
Illustrative single-chain example, with one working calendar and no parallel work or additional constraints.
The baseline chain is excavation, three days; reinforcement, three days; concrete, two days. At the data date, excavation is finished. Reinforcement has not started, and the revised crew assessment gives it four remaining days.
| Activity | Original remaining duration | Revised remaining duration |
|---|---|---|
| Reinforcement | 3 working days | 4 working days |
| Concrete | 2 working days | 2 working days |
| Total remaining chain | 5 working days | 6 working days |
The simplified completion forecast moves by one working day. In a real programme, another path or a constraint may govern completion, so examine the network rather than adding durations across unrelated activities.
A useful update narrative
Report the data date, changed milestones, progress achieved, causes of slippage and the next actions. Separate observed facts from assumptions about future output. A clear explanation should let a project manager understand why the finish date moved and what decision is needed.
- Which work package drives the current forecast?
- Which remaining durations changed, and why?
- What approvals or resources are needed in the next reporting period?
- Is recovery being assessed, or is the movement part of a delay event?
Use recovery planning to compare corrective scenarios, and delay analysis when an event needs a separate assessment.
Common questions
What is the data date?
It is the cut-off separating recorded progress from the remaining forecast. Use one agreed cut-off and consistent evidence for the update.
Does a progress update change the approved baseline?
An update should preserve the distinction between actual progress, the current forecast and the approved baseline. Baseline revision requires the applicable project approval process.
Can a high percentage complete still hide a late finish?
Yes. The remaining critical work and its dependencies can drive completion even when much of the total quantity is finished.
What is the difference between Retained Logic and Progress Override?
They decide how out-of-sequence progress is scheduled. Retained Logic keeps the remaining work dependent on its predecessor; Progress Override ignores that logic for the started activity. Use the setting your project requires — Nexora calculates both.
Can I import my P6 update and continue in Nexora?
Yes. Import the XER with its actuals, calendars and constraints, update at the new data date and export the statused XER.
Does Nexora calculate earned value and S-curves?
Yes — planned, earned and actual values with SPI and CPI, and cumulative S-curves from the cost-loaded programme.